August, 15th 2019 - This release includes a big update on Post-Processing worklists in the Agile MES

[Agile MES] Dynamic Worklists (BETA)


Worklists are used to display and track all Postthe production and post-processing activities in the production schedule of and steps on your shop floor. The Agile The Agile MES will automatically creates generate a Dynamic WorklistsWorklist for each print job, station that requires Postpost-processing. As Since each part can have an individual workflow and set of requirements after printing, the Worklists worklists are essential for tracking to track the individual progress

To learn more about the worklists, here are the key functionalities: 

...

, the production steps and ensure an audit trail for each part.

Key Functionalities


Automatically Adjusting Worklists

Every time a Job is moved, added , scrapped & or rescheduled or deleted the Agile MES will automatically reschedules reschedule the parts part worklists based on the available capacity in your production schedule. In this BETA beta release your parts are scheduled adjusted based on first-in-first-out. The full release will optimize your production schedule based on the target of delivery date for each part. 

It is now also possible to scrap or delete Jobs and which will remove all the planned Worklists related to the job.

Image Added

...

Changing the Workload

...

Capacity within a

...

Worklist

By clicking on a worklist,   processing operators can view all parts , that need are scheduled to be processed on a workstation in one each day. This workload  can can be changed by manually removing or adding parts from to the worklist.

  • Operators will /Engineers should remove parts if the workload includes more parts than they can process in a day.
  • Operators will should add parts if they want to prioritize parts from another worklist in the future. 

...

  • other future worklists or know that they can handle more parts in a single day.

After adjusting the part workload the worklist can be confirmed be confirmed and the parts are will be marked as ready to be processed. 

Track & Document the Part Progress in Worklists

As Operators process parts, they can document their progress in the worklist

Image Added


Tracking and Documenting Progress using Worklists

Operators and engineers can document all progress on the worklist as they process parts. The Agile MES automatically tracks when a part arrived at a workstation so that you can compare the planned arrival and  the the actual arrival time of a part. A Part part can be set to the following statuses:  

  • In Progress: The processing of a part has started
  • Complete: The processing of a part is successfully completed. The part is automatically marked as `arrived` arrived in its the following workstation’s worklist.
  • Moved to next day: The processing of the part has not started and the part is rescheduled to for the next day.  
  • Scrapped: During the processing, the part was damaged and needs to be reprinted. A new part sequence is automatically created that needs to be scheduled for production.

The part staus will also be indicated with Worklist Colors:

  • Light Purple: no/some parts arrived,
  • Purple: parts arrived
  • Blue: worklist is confirmed
  • Green: All is completed except moved light
  • Red: some parts scrapped red: all parts scrapped

In this release, we included the BETA version 

  • [B3-5989] - Move Parts to this day
  • [B3-5923] - Finishing a Job deletes some of the existing worklists
  • [B3-5928] - Setting a workstations processing time to 0 does not save
  • [B3-5997] - Distinguish scheduled sequence group (not arrived) from arrived sequence group
  • [B3-6002] - Delete a job that has started or finished
  • [B3-6003] - Delete a job that is finished and workstation is confirmed
  • [B3-5931] - Worklist confirmation not working
  • [B3-5990] - [FE] Confirm a worklist when parts not arrived
  • [B3-5384] - [Backend] Moving/Adding/Scrapping/Deleting Jobs should change derived sequence group allocation in Worklists
  • [B3-5385] - [Backend] Changing Worklist Workload should reassign sequence groups
  • [B3-5386] - [Backend] Sequence group status update: in progress/complete/scrapped/moved
  • [B3-5387] - [Backend] Sequence group should have an arrived time
  • [B3-5388] - [Backend] Refactor job to use sequence group
  • [B3-6000] - [FE][BE] Worklist colors
  • [B3-5927] - [Agile MES] Scheduling stops when reaching a workstep without a workstation assigned

Bug

...


Image Added

Other notable changes and fixes:

  •  [Checkout] - Editing Shipping address no longer returns to Home
  •  [Agile MES]: DoesNotExist: Worklist matching query does not exist .
  • [B3-5856] - "user email includes" works for scripted pricing
  • [B3-5874] - Editing Shipping address returns to Home
  • [B3-5922] - [fixed
  •  [Agile MES]  Scheduling a Job automatically sets the sequence groups status to printing
  •  [B3-5940] - [frontend] - fix the shared vuex common/user/actions[B3-5953] - Service Panel] Have the "send email" not selected if the "send email" option is not selected in the admin panel
  •  [Service Panel] "user email includes" now works for scripted pricing
  •  [Service Panel] minor service panel bugs fixed
  •  [B3-5963User Panel] - Order CSS fixes
  •  [B3-5964User Panel] - Language for serializers isn't correct[B3-5991] - [FE] Loading Re-introduced loading indication after clicking on buttons
  •  [B3-6020Basket] - Wall thickness analysis is applying now to every part uploaded
  • [B3-6071] -  [Basket] Improved stability and performance of material list loading
  •  [Frontend] Language for serializers isn't correct
  •  [Frontend] Fixed the shared vuex common/user/actions

New Feature

  • [B3-4733] - [Backend] Models & AbstractSalesTransactions
  • [B3-5778] - [Backend] Save basket as Request view
  • [B3-5947] - [EvalJS] Await JavaScript Promises

...

  • [B3-5864] - [Backend] Move "Billing address required" Flag to Partner

Improvement

  • [B3-5364] - [Frontend] Refactor useNewCheckout usage in the service panel
  • [B3-5557] - [Frontend] Bring back the list of supported file formats.
  • [B3-5840] - Have the "send email" not selected if the "send email" option is not selected in the admin panel[B3-5982] - [FE]Frontend] Refactor billing address
  • [B3-6047] - [backendBackend] Rename /request-for-quote/ to /requests-for-quote/

Other Notable Changes and Bugfixes 

...

  • [Backend] Move "Billing address required" Flag to Partner




If you are interested in testing our upcoming tools as early adopters or have any further questions, please feel free to contact our product team.

...